Pengcheng Column Formwork System
Introduction
two piece of semi-circle film faced plywood panels with U.N slots at edges are connected seamlessly
and steel belts with screws reinforce it.
Usage
concrete forming of circular columns or pillars in construction.
Specification
Diameter(mm) | Thickness(mm) | Height(m) | Pieces |
200-550 | 15 | 3 Max | 2 |
600-1200 | 18 | 3 Max | 2 |
1250-1500 | 22 | 3 Max | 2 |
1600-2200 | 22 | 2.4 Max | 4-6 |
P.S: the heights above 3m by more pieces connected well.
Features
1, light weight and easy installation
Selected high quality birch and poplar film faced plywood as raw materials, Pengcheng formwork
is light weight, high strength, and easy installation.
Example: Pengcheng formwork at 1000mm diameter and 3m height is about 40-45 kgs and 2 or 3
workers can install it well by hands. If to use steel formwork in the same size, it have to make use
of hoisting equipment.
2, accelerate the construction schedule and shorten the construction period
Normally, a group of workers (2 or 3 people) have installed about 10-15 circular columns within 8 hours, which will
save 70% construction period compared with steel circular column formwork.
3, easy-cutting, solve lintel problems between circular columns and beams
Pengcheng formwork can be cut according to architectural drawings and successfully solve connection between
circular columns and beams, which is more flexible than steel formwork.
4, perfect concrete surfaces
5, lower cost
Pengcheng formwork is made of film faced plywood, shorter construction period, and lower labor cost. Best choice to replace traditional expensive steel circular column formwork.
Technical dates
No. | Testing | Dates | |
1 | Moisture | 8-12% | |
2 | Bonding strength | 800mm | 1.27Mpa |
1000mm | 1.36Mpa | ||
3 | Bearing capacity | 800mm | 20.2KN |
1000mm | 18.9KN |
Installation
P.S: reinforcement by concrete 0.5cm-1cm above ground
strength by steel belts with screws every 20cm-30cm
fixed by wooden blocks and scaffolding every 50cm-150cm
one times concrete forming within 7m height, two times concrete forming above 7m every 30-60 minutes
Maintain and Storage
keep the phenolic resin film well and clean the surfaces well after using it.
oil treament and 20mm above ground for long-time storage.
Shippment
Raw materials and Accessories
Raw material | Film faced plywood | Core: birch and poplar |
Glue: waterproof melamine | ||
Film: brown film | ||
Hot pressing: two times | ||
Surface treatment: sanding | ||
Edges: U.N slots by cutting machine | ||
Accessories | Steel belts | Steel No.: Q235 |
Width: 3.2cm | ||
Thickness: 1.2mm | ||
Extension strength: 650Mpa/mm² | ||
Extension length: ≤4mm/m | ||
Screws | 8.8 grade M12 |
Compare
Items | pengcheng formwork | steel formwork | PVC formwork | DIY wooden strip formwork |
Performance | lightweight,strong resistance to pressure, good insulation and air permeability | solid and durable, but heavy weight, bad insulation and air permeability | lightweight, but bad insulation and air permeability | bad insulationand air permeability |
Installation | by hands, only 1 days | by hoisting equipment, about 4 days | by hoisting equipment, difficult for dismounting | difficult for assembling wooden strips |
Cut | yes, solve connection problem between circular columns and beams | no, the flexbility is bad | yes, but bigger joint-cutting | no |
Construction period | only 4 days | about 15 days | about 7 days, lower percent of pass | about 15 days,lower percent of pass |
Cost | made from film faced plywood, short construction period, don't need hoisting equipment, economical and practical | made from steel plates, operation by hoisting equipment, expensive | made from PVC, cheap | high labor cost |
Analysis of construction projects
Take the example of Tai’an Culture and Art Center Project: the diameter of its circular columns have 400mm, 700mm, 800mm, 900mm, and 1200mm, different heights from 3m to 6m, 800 circular columns in totally.
Through our PENGCHENG formwork, it only takes 5 days. The total cost is about USD 110,000.00.
If to make use of STEEL formwork, it will need 15 days and the cost will be USD260,000.00, including the expense of hoisting equipment.
If to take advantage of PVC formwork or DIY wooden strip formwork, they can’t guarantee the construction period.
Gallery